Humboldt County Commission revokes Jungo Land & Investment’s CUP extension Print
Written by Dee Holzel/Photos by Michael Michaelsen   
Tuesday, April 06 2010 04:20

Humboldt County DA Russell Smith, Commission Chairman Chuck Giordano, Commissioners Garley Amos and Tom Fransway WINNEMUCCA — With just seven days left on their conditional use permit (CUP), the company seeking to develop a class 1 landfill on Jungo Rd. lost the 5-year CUP extension that was necessary for the project to move forward.

The Humboldt County Commissioners voted unanimously Monday afternoon (April 5)  to revoke the extension previously granted by the Regional Planning Commission (RPC). 

Jungo Land & Investments can appeal and seek judicial review of the decision, but the state permits necessary to move forward with developing a class 1 landfill require an underlying CUP.  The company was granted the existing CUP on April 12, 2007, which required they obtain the necessary permits and get started on the project within a three-year time limit.  In February 2010, the company was granted a five-year extension by the RPC.

Robert Dolan successfully argued for the revocation of the CUP extension Robert Dolan filed and won on appeal claiming the RPC abused their discretion in issuing the permit extension because Jungo Land & Investments failed to show good cause the extension was necessary. Dolan was joined in the appeal process by Massey K. Mayo, both of Dolan Law Offices.

The loss of the extension was seen as a victory for anti-landfill forces.  After the hearing, Dolan commented, “I’m grateful to the Humboldt County Board of Commissioners who reversed the decision of the RPC.”

“I am most thankful for the citizens of Humboldt County who stood up to protect the beautiful desert and quality of life we have here,” Dolan continued. “If not for the committed work of those citizens the decision might have been different.”

During the appeal hearing, Dolan successfully argued Jungo Land & Investments had not committed the time and resources to move the project forward during the three years already granted to them.

The RPC may grant CUP extensions if evidence shows there was just cause for the delay, but Dolan argued that was not the case in the matter at hand.  Reviewing the timeline, he pointed out Jungo Land & Investments waited a year before filing for the solid-waste permit and 21 months before filing for the air quality permit.

John Frankovich attempted unsuccessfully to argue community activism delayed the project Jungo Land & Investments was represented at the appeal hearing by John Frankovich of McDonald Carano & Wilson, of Reno, who countered the project was delayed by community activists attempting to derail the project.

Testifying for Recology, the parent company of Jungo Land & Investments, was Executive Vice President and Chief Operating Officer George McGrath and Project Manager Erin Merrill.

Under questioning, Merrill said the operating permit process was only anticipated to take nine months -- or so. She said the process was delayed – in part – because the Nevada Department of Environmental Protection (NDEP) had to respond to community concerns that didn’t surface until the company was more than two years into the project.

In addition, the company had numerous appeals filed by Dolan and Mayo at the state and local level that required response.

Merrill attempted to explain to the commissioners the company did move forward with the project.  She said before the operating permits were filed, there were numerous environmental and engineering studies conducted by the company – to the tune of about $1 million.

It was also noted the company actually began preliminary permitting discussions with the NDEP in 2006. In addition, Merrill explained the company turned in draft permits to the NDEP, whose representatives identified issues for Recology to mitigate.

During closing arguments Frankovich noted the extensive steps taken by community activists to delay the project, which included multiple appeals, judicial review of the CUP, and appeal of the NDEP-issued air-quality permit – all but one of which is still pending and were not filed until the last six months of the CUP.

He commented, “Don’t sit here and say ‘you could have proceeded with the project’ when you had the permits under attack.”

He reiterated his understanding of the Humboldt County Code, which granted exclusive right for CUP extensions to the RPC – not the Humboldt County Commissioners.

Dolan countered under the county code the commissioners have the right to review all decisions made by the RPC – even though CUP extensions were not specifically mentioned.

He restated his belief Jungo Land & Investments did not commit the resources necessary to complete the project and they misrepresented the facts on the CUP application.

“If they create issues for appeal, they don’t get the benefit of the delay,” he said.

After discussion, the commissioners voted unanimously to revoke the 5-year CUP extension granted to Jungo Land & Investments.  They agreed the company did not move forward in a timely manner to meet the conditions of the original CUP.

“Jungo blames this community – specifically three housewives – for their troubles,” Commissioner Tom Fransway noted in reference to the founding members of Nevadans Against Garbage (NAG).  He went on to say it was Jungo's own procrastination that resulted in their inability to meet the terms of the CUP.

The only real dissenter was Commissioner Garley Amos who said he believes in the rights of private property owners, and he went on to say it was his preference the matter by reviewed by the court.

The other commissioners noted that’s probably what would happen if the extension was revoked, so Amos voted with the other commissioners to revoke the extension.

Prior to the meeting participants expected some debate about whether or not Fransway would be permitted to participate in the appeal.  Frankovich asked that Fransway be recused for bias, since he has taken a public anti-landfill stance.

In a written response Humboldt County DA Russell Smith agreed bias existed, and he advised the commission to take action if Fransway didn’t recuse himself. However, once the hearing actually started the matter was briefly mentioned by Frankovich but not brought up again by either side. 

Fransway previously said he would not recuse himself.

Jungo Land & Investments still has options open to them for the development of the class 1 landfill at the proposed Jungo Rd. site -- including the option of going back and seeking a new CUP.  Representatives of the company were not available after the hearing for comment.

Additional news on the CUP extension:

RPC extends landfill CUP for five years

Dolan appeals landfill extension to county commission

County commission sets appeal hearing

News on the air-quality permit:

NDEP issues air quality permit for proposed Jungo Rd. landfill

Dolan vows to appeal NDEP decision - vows to fight on

Dolan and Mayo appeal Jungo air-quality permit

News on the judicial review of the CUP:

RPC denies CUP appeal - heated dispute erupts

Commission upholds RPC decision on a split vote 

Landfill appeal heads to District Court

District Court sets date for landfill appeal

 
FacebookTwitterGoogle Bookmarks

Add comment

Comments will be reviewed prior to publishing, and may be edited for style and clarity. Your email address will not appear on the site.


Security code
Refresh

Related Items

mini- Calendar

S M T W T F S
week 18 1 2 3 4 5
week 19 6 7 8 9 10 11 12
week 20 13 14 15 16 17 18 19
week 21 20 21 22 23 24 25 26
week 22 27 28 29 30 31

Events...

Mon May 21 @09:00
Board of Commissioners
Mon May 21 @10:45
Joint City/County Meeting
Tue May 22 @16:30
HCSD Board of Trustees
Thu May 24 @17:30
HGH Board of Trustees

In your opinion...

Would you support using taxpayer dollars to buy and renovate the Winnemucca Hotel for local use?
 

Who's Online

We have 300 guests online

Newest comments

  • Overkill........just like Quintin's temper? Just l... More...
  • Yes, Editor, thank you, we forgot that. You don't ... More...
  • This young man is not home yet, per family he is d... More...
  • Why didn't the community have the opportunity to v... More...
  • Council and Commission - visit Elko and Sparks and... More...

Statistics

Content View Hits : 1344586